Plumbing and heating installations for a new build in Putten
In Putten we work as a subcontractor on a new-build project. AZGS carries out all plumbing and heating installations. The work started in early November 2026 and runs for about a year.
- Location: Putten
- Type: Business project, as a subcontractor
- Status: In progress (started November 2026)
- Work: Plumbing and heating installations
- Duration: About one year

The situation
A new building is being added next to an existing one. The first phase is the underground drainage, with connection points where the sanitary facilities will be installed later.
What we did
- Laid the PVC drainage pipes in the trenches.
- Fitted bends and branches along the facade of the new building.
- Placed vertical connection points for the future sanitary facilities and capped them to keep sand out of the pipes.
Photos of the work



Current status
The project is in progress. We will add the next phases to this page as the work continues.